WASHINGTON, July 2 (DC Times Online) — The U.S. Department of Energy issued an emergency order under Section 202(c) of the Federal Power Act for PJM Interconnection’s region after the grid operator warned of an “imminent electricity reliability emergency” as a heat wave drove demand toward record levels.
PJM said in its June 29 request that peak load could reach about 159,563 megawatts on July 1 and about 162,860 megawatts on July 2. The order applies to a grid that serves 67 million customers across the Mid-Atlantic, South and Washington, D.C.
The warning lands as extreme heat and rising electricity use from data centers strain the system. In a May report, PJM executives said there was a “fundamental mismatch between how fast demand is growing and how quickly new supply can be built and connected to the grid,” and said hyperscale data centers were “adding load at an unprecedented pace.”
The heat wave was forecast to push temperatures above 100 degrees from Boston to Washington, including near Northern Virginia’s data center hub, adding to air-conditioning demand. PJM forecast summer demand of 166.3 gigawatts for Thursday evening, above its prior summer record of 165.6 gigawatts set in 2006.
PJM said it has about 180.2 gigawatts of generation capacity and 8 gigawatts of demand-response resources that pay customers to cut use during emergencies. Its June operating data showed the strain this month: the grid operator issued a Hot Weather Alert for June 22-26, then a Maximum Generation Alert, and said demand response reduced load by more than 4,000 megawatts during the heat wave.
PJM’s long-term forecast puts summer peak demand at 220,000 megawatts over the next 15 years.